Appendix 11.2.8
Targets and achievements of distribution infrastructure during 2019-20
Sl. No. Item Target Unit Achievement Unit Percentage of achievement
1 11kV lines 1080.5 km 1939 km 179.45%
2 Distribution Transformer 1301 Nos. 2023 Nos. 155.50%
3 LT lines 3689.14 km 3688 km 99.97%
4 Service connections 291517 Nos 380584 Nos. 130.55%
Source: KSEBL