Appendix 11.1.16 List of completed and on-going projects under KSTP Phase II with State fund, 2020-21 (in Rs crore)
Sl.No Name of work Revised contract amount Financial Progress as on May 31, 2020 Physical Progress (per cent) Remarks
1 UG 1-Kasaragod-Kanghangad Road (27.78 km) 114 123.2 100 Completed
2 UG 2-Pilathara-Pappinisserry Road (20.90 km) 102 103.28 100 Completed
3 UG 3 A-Thalassery-Kalarode Road (28.80 km) ( Re-arranged) 156 126.96 93.4 Road work completed; Eranholi bridge approach to be completed.
4 UG 3 B Kalarode-Valavupara (25.20 km) (Re-arranged) 200 204.33 95.99 Road work completed. Koottupuzha bridge to be completed.
5 UG 4-Chengannur-Ettumanoor Road (47.70 km) 288 278.06 100 Completed
6 UG 4 A-Thiruvalla Bye pass (2.3 km) 37.03 22.67 100 Completed
7 UG 4 B-Thiruvalla Town (2.00 km) 7.77 4.83 100 Completed
8 UG 5-Ettumanoor-Muvattupuzha Road (40.12 km) 159 164.71 100 Completed
9 UG 6-Ponkunnam -Thodupuzha Road (50 km) 270 223.71 100 Completed
10 UG 7-Perumbilavu-Perinthalmanna Road (39.37 km) 8.11 7.58 100 Completed
11 Safe Corridor Demonstration Project Kazhakuttam-Adoor 146.67 129.35 100 Completed
Source: KSTP