Appendix 11.1.28 -
OVERALL PROGRESS OF CONSTRUCTION WORKS OF VISL
| Sl No | Components | Total Quantity | Actual Achievement | Progress in per cent |
| 1 | A.Breakwater | 2960 meters | • Core layer: Placement & profiling of core layer completed. • Armour layer: Placement & profiling of armour layers completed except for a length 436 meters (between BR1 to BR2 stretch) • Accropode layer (from chainage 676 m to chainage 2959 m): up to chainage 2800 m fully completed • Wave wall (from chainage 676 m to chainage 2959 m): upto chainage 2800 m completed |
97% |
| 2 | B.Reclamation | 61.374 Hectares | • Reclamation works completed. • Additional reclamation of 2.055 Ha also carried out for future development area |
100% |
| 3 | C. Dredging | • Exterior approach channel: -20.8 m CD • Inner approach channel: - 18.4 m CD • Turning Circle: - 18.4 m CD • Berth pocket: -18.4 m CD |
Required depth achieved in the outer & inner approach channel, turning circle & berth pockets. | 100% |
| 4 | D. Container Berth | 800 meters X 53 meters | All works completed | 100% |
| 5 | E. Container Yard | 30 Ha (920 meters x 330 meters) | completed | 100% |
| 6 | F. Port Equipment | • 32 Nos. of cranes • 4 tug boats • 2 mooring launches • 1 pilot-cum-survey vessel | all equipments delivered | 100% |
| 7 | G. Utilities & Others | 100% | ||
| 8 | H. Gate Complex & Road Development | 97% | ||
| Overall physical progress | 98% | |||
Source: VISL