Appendix 11.1.28 -
OVERALL PROGRESS OF CONSTRUCTION WORKS OF VISL

Sl No Components Total Quantity Actual Achievement Progress in per cent
1 A.Breakwater 2960 meters • Core layer: Placement & profiling of core layer completed.
• Armour layer: Placement & profiling of armour layers completed except for a length 436 meters (between BR1 to BR2 stretch)
• Accropode layer (from chainage 676 m to chainage 2959 m): up to chainage 2800 m fully completed
• Wave wall (from chainage 676 m to chainage 2959 m): upto chainage 2800 m completed
97%
2 B.Reclamation 61.374 Hectares • Reclamation works completed.
• Additional reclamation of 2.055 Ha also carried out for future development area
100%
3 C. Dredging • Exterior approach channel: -20.8 m CD
• Inner approach channel: - 18.4 m CD
• Turning Circle: - 18.4 m CD
• Berth pocket: -18.4 m CD
Required depth achieved in the outer & inner approach channel, turning circle & berth pockets. 100%
4 D. Container Berth 800 meters X 53 meters All works completed 100%
5 E. Container Yard 30 Ha (920 meters x 330 meters) completed 100%
6 F. Port Equipment • 32 Nos. of cranes • 4 tug boats • 2 mooring launches • 1 pilot-cum-survey vessel all equipments delivered 100%
7 G. Utilities & Others     100%
8 H. Gate Complex & Road Development     97%
Overall physical progress 98%

Source: VISL