Appendix 11.1.7
Hill Highway stretches approved by KIIFB
| Sl. No | District | Length (km) | Stretch | Approved Outlay (in crore) |
Physical Progress | Remarks |
| 1 | Thiruvananthapuram | 15.495 | Kudappanamoodu- Parassala | Rs 76.90 | 100% | Work Completed |
| 2.748 | Kudappanamoodu- vazhichal | Rs 15.66 | 98.00% | Work in Progress | ||
| 7.85 | Vazhichal - Kallikadu | Rs 41.23 | 97% | Work in progress (Eviction to be completed) | ||
| 9.45 | Koppam - Peringamala | Rs 50.81 | 88% | Work in progress | ||
| 21.08 | Kallikadu - Aryanadu, Iruthalamoola - Vithura, Palode - Challimukku | Rs 54.71 | 100% | Works completed | ||
| 2 | Kollam | 46.1 | Kollayil (Challimukk) - Punalur KSRTC | Rs 201.67 | 100% | Works completed |
| 3 | Kottayam | 7.5 | Placheri - Karinkallumoozhi | Rs 33.20 | TS stage | Stage 2 forest clearance to be obtained.PED under preparation |
| 4 | Idukki | 5.25 | Elakkal bridge to Valiya Mullakanam | Rs 39.80 | 40% | Works in progress |
| 27.717 | Peerumedu - Devikulam | Rs 144.09 | Phase 1 - 80% Phase 2-100% Phase 3-70% |
Works is divided into 4 stretches. Work started in 3 stretches. Phase 1 -Work in progress 80% Phase 2-Work Completed Phase 3-Work in progress70% Phase 4-PED under preparation |
||
| 19 | Chappath - Kuttikanam | Rs 104.58 | 100% | works completed | ||
| 5 | Ernakulam | 23.269 | Vettilappara- Eucaly | Rs 105.02 | TS stage | Forest clearance to be obtained. Boundary marking to be initiated. |
| 6.16 | Eucaly - Illithode | Rs 34.84 | TS stage | Free surrender issues | ||
| 1.895 | Illithode- Chettinada | Rs 32.09 | TS stage | Free surrender issues | ||
| 17 | Chettinada - Cheranganal | Rs 76.26 | TS stage | Free surrender issues | ||
| 13.7 | Cheranganal- Nadukani- Neriamangalam | Rs 65.57 | TS stage | Free surrender and forest clearance issues | ||
| 6 | Thrissur | 5.3 | Pattikad - Vilangannur | Rs 21.37 | 100% | Works Completed |
| 30.84 | Vilingannur- Vellikulangara | Rs 136.49 | TS stage | Free surrender issues | ||
| 19 | Vellikulangara to Vettilappara bridge | Rs 124.69 | 10% | Work in progress | ||
| 7 | Palakkad | 18.1 | Kanjirampara - Kumaram puthoor | Rs 91.41 | 5% | Works in progress |
| 14.86 | Gopalapuram- Kannimarimedu | Rs 73.21 | TS stage | TS estimate under preperation | ||
| 15.73 | Kannimarimedu - Nedumani | Rs 82.56 | TS stage | TS estimate under preperation | ||
| 7.057 | Panangattiri to Vithanassery | Rs 33.18 | TS stage | TS estimate under preperation | ||
| 15.21 | Nenmara Bypass end to Thankom Junction | Rs 75.83 | TS stage | TS estimate under preperation | ||
| 8 | Malappuram | 11 | Kakkadampoyil- Moolepadam | Rs 80.03 | Tender stage | works tendered on 22-03-2025. |
| 20.5 | Pookottumpadam - Moolepadam | Rs 101.82 | 80% | works divided to two parts. Works of 1st part completed and 2nd part tendered on 22-03-2025. | ||
| 21.01 | Pookottumpadam – Kalikavu – Kerala estate – Kizhakkethala- Karuvarakundu | Rs 131.61 | 85% | works arranged as two stretches-Work completed in 1st stretch and 70% in 2nd stretch | ||
| 12.275 | Chirakkal to Ucharakkadavu, Ucharakadavu- Kanjirampara | Rs 50.58 | Tender stage | works tendered on 29-03-2025 | ||
| 9 | Kozhikode | 12 | Maripuzha - Anakkampoyil- Pullurampara | Rs 108.16 | 23% | Work in progress |
| 5.446 | Chunkakutty - Poothampara bridge | Rs 38.47 | Tender stage | Tender stage | ||
| 7.225 | Poothampara bridge- Moonamkai- Thottilpalam | Rs 45.34 | TS stage | TS estimate under preperation | ||
| 6.4 | Thottilpalam- Mullankunnu | Rs 29.77 | Tender stage | Work tendered on 28-03-2025 | ||
| 8.06 | Mullankunnu- Peruvannamuzhi | Rs 38.39 | TS stage | Free surrender of land in progress | ||
| 15.65 | Peruvannamuzhi- 28th mile | Rs 71.94 | 4% | works arranged as two stretches-35% in 1st stretch and 2nd stretch is in tender stage | ||
| 6.8 | 28th mile- Thalayad | Rs 50.32 | 70% | Work in progress | ||
| 16.822 | Thalayad Kodenchery | Rs 106.09 | 20% | divided in to 2 strteches. Strtech 1 - 80% and Stretch 2 - 20% | ||
| 35.35 | Kodenchery Kakkadampoyil | Rs 221.20 | 100% | Works completed | ||
| 10 | Wayanad | 43 | Boys Town- Mananthavady- Kalpetta and Valad - Kunkichira | Rs 186.65 | 70% | Work in progress |
| 16.75 | Kalpetta bypass Meppadi Kappankolli Chooralmala Arunappuzha(Malappuram) | Rs 63.78 | 60% | Balance work in progress | ||
| 8.521 | Kunhome- Chunkakutty | Rs 36.52 | 15% | Work in progress | ||
| 11 | Kannur | 25.3 | Vallithod Ambayathod | Rs 83.16 | 83% | Work in progress |
| 5.76 | Ambayathod - Boys Town | Rs 35.67 | TS stage | TS stage | ||
| 12 | Kasaragod | 23 | Nandarapadavu Chevar | Rs 54.76 | 100% | Completed |
| 27.97 | Chevar Edaparamba | Rs 86.64 | 88% | Works in progress | ||
| 24.4 | Kolichal – Edapparamba road | Rs 85.15 | 80% | Work foreclosed excluding forest portion | ||
| 28.877 | Kolichal Cherupuzha | Rs 89.24 | 98% | Work foreclosed excluding forest portions |
Source : Kerala Infrastructure Investment Fund Board, Government of Kerala