Appendix 4.6.29
Performance of CAPEX
| Period | No of factories | No of workers | No of working days | Total employment (Man days) | Turnover (Rs in lakh) | Profit/Loss (Rs in lakh) |
| 2012-13 | 10 | 5,059 | 265 | 1,340,635 | 6,882.94 | -16.04 |
| 2013-14 | 10 | 4,796 | 212 | 1,016,752 | 6,347.86 | -945.73 |
| 2014-15 | 10 | 4,190 | 232 | 972,080 | 7,385.74 | -1445.95 |
| 2015-16 | 10 | 3,785 | 207 | 783,495 | 7,371.00 | -1641.37 |
| 2016-17 | 10 | 3,400 | 120 | 408,000 | 4,584.63 | -982.35 |
| 2017-18 | 10 | 4,050 | 148 | 599,400 | 8,686.84 | -1259.00 |
| 2018-19 | 10 | 3,980 | 190 | 756,200 | 7,650.95 | -1980.79 |
| 2019-20 | 10 | 4,209 | 206 | 867,054 | 8,518.98 | -1695.01 |
| 2020-21 | 10 | 4,130 | 142 | 586,460 | 4,688.66 | -1756.07 |
| 2021-22 | 10 | 4,100 | 179 | 733,900 | 6,315.48 | -2223.85 |
| 2022-23 | 10 | 3,970 | 93 | 369,210 | 5,390.20 | -1103.98 |
| 2023-24 | 10 | 3,797 | 155 | 588,535 | 5,440.61 | 1887.22 |
| 2024-25* | 10 | 3,592 | 165 | 592,680 | 5,671.08 | 758.45 |